Clarifiction on terminating the primary data center

$
0
0
I've been trying to author a process for a datacenter switchover in the event a disaster with our primary datacenter. I'm looking on some clarification on Step 1. Since DAG members must be marked as down, would I run the Stop-DatabaseAvailabilityGroup without the -ActiveDirectorySite and -ConfigurationOnly parameters if my scenario is such that Exchange and ActiveDirectory is completely inaccessible? Just curious. Unfortunately, we don't have a lab setting to walk through these steps.